09/05/2014 - Ground Leveling
09/12/2014 - Official Construction start date
Plumbing work and inspection
09/16/2014 - Concrete poured / Slab inspection
09/19/2014 - First level framing done
09/24/2014 - Second level framing done
09/30/2014 - Cement pouring for bathtub/ Electric work and inspection
10/02/2014 - Siding and brick veneer in the front of the house started. Windows are up.
Shingles on roof.
10/06/2014 - Pre DryWall meeting
Drywall started same day. PM said it would take 5 business days
10/10/2014 - Drywall done and first coat of painting done.
10/15/2014 - Carpentry work, doors cabinets closets done.
10/16/2014 - Tiles and Vinyl floor work done
Construction Progress Photos:



09/12/2014 - Official Construction start date
Plumbing work and inspection
09/16/2014 - Concrete poured / Slab inspection
09/19/2014 - First level framing done
09/24/2014 - Second level framing done
09/30/2014 - Cement pouring for bathtub/ Electric work and inspection
10/02/2014 - Siding and brick veneer in the front of the house started. Windows are up.
Shingles on roof.
10/06/2014 - Pre DryWall meeting
Drywall started same day. PM said it would take 5 business days
10/10/2014 - Drywall done and first coat of painting done.
10/15/2014 - Carpentry work, doors cabinets closets done.
10/16/2014 - Tiles and Vinyl floor work done